Bay View Elementary

Evolving New Master Implementation Plan
In working with the Architects and the site staff the plan of action is coming together.

Implementation Plan


Original Master Plan Information.
Bayview Elementary project plan

Existing Campus

Background:

Bayview Elementary, established in 1950, is a multi-cultural, neighborhood school composed of several classroom buildings and other structures arranged in a traditional finger plan arrangement with north –facing window walls.

  • Current Enrollment: 570 Students
  • Enrollment Projection: 506 in 2021 / 482 in 2025
  • Building Area: 55,843 SF
  • Approximate Site AC: 5.821 Acres
  • Modernization Eligibility: $1,577,806

Community and Staff Priority Survey

This survey represents input from staff, students, parents, and community as collected during community meetings, school meetings, and online surveys

Top 10 projects in order of importance with 1 being the highest priority.

  1. Remove Portable Classroom Buildings
  2. Technology Infrastructure Upgrades
  3. Improve the Quality of the Existing Play Fields
  4. Expand Play Fields
  5. New Interior Finishes/Lighting/Cabinetry
  6. Nature Based Play equipment
  7. Modernize Existing Cafeteria & Kitchen
  8. Improve Parking Lot Circulation & Drop-off
  9. Campus Security
  10. New Multi-Purpose Building

Note: This list was reviewed and considered by the steering committee in making appropriate project priority recommendations.

Bayview Elementary

IDENTIFIED CAMPUS NEEDS AND SUGGESTED IMPROVEMENTS

  • Re-roof existing permanent buildings
  • New 2-story classroom building to replace portables
  • ADA site improvements
  • Reconfigure and/or add to parking lot to improve circulation and student drop-off
  • Repaint exterior of entire campus
  • New multi-purpose to free-up space for
  • Improve campus security: fencing, lighting and cameras
  • Construct a nature based play equipment near the existing play fields
  • kindergarten/pre-k at front of campus
  • Re-purpose triangular parking lot into Kindergarten play equipment
  • Install new campus-wide HVAC system
  • Expand the play field areas if portable classrooms are removed
  • Fix flooding problems, storm drainage system
  • Relocate Administration offices closer to main parking
  • Construct new multi-purpose building
  • Replace existing landscaping and irrigation with drought tolerant plants and water efficient irrigation
  • area for supervision and easier access
  • Bay View Elementary School
  • New campus utility infrastructure; electrical
  • Reconstruct play fields to eliminate hazards (low/high spots), replant turf, install new water efficient irrigation

Improvements/needs noted are based upon Architect and Engineer assessments of facilities as well as Facilities Staff.